Project: 11 Murray Rose Avenue (Site 8D)
Early Works Site 8D (Bulk Earthworks & Construction of 2 basement levels)
Other '11 Murray Rose Avenue (Site 8D)' Jobs
Job Details
| Job Title |
DA 11-09-2016 |
| Project Type |
Demolition |
| Status |
Approved |
Attachments & Resources
| Determination |
|
| Assessment Report |
|
Key dates and other information
| Status information |
development has been approved subject to conditions |
| Applicant information |
http://fdcbuilding.com.au/ |
| Development Location |
11 Murray Rose Ave, Sydney Olympic Park NSW 2127 |
| Applicant website |
http://fdcbuilding.com.au/ |
DA 11-09-2016
|
| Development type |
Demolition |
| Application # |
DA 11-09-2016 |
| Investment value of works proposed |
$5,690,000.00 |
| Date Application made |
30/09/2016 |
| Date Application Determined |
15/11/2016 |
| Gross Determination Time (days) |
46 |
| Decision |
N/A |
| File Record |
f16/780 |
|
For further information, please contact Town Planner: Dat Tran via email
dat.tran@sopa.nsw.gov.au